Traffic Signal Intersections

Installation, implementation and construction of systems including but not limited to:

  • Traffic Signals and Lamps
  • Steel or Aluminum Poles and Arms
  • Pedestrian Signals
  • Underground and under road conduit and wire
  • Junction Boxes and Foundations
  • Traffic Controllers
  • Fire Signals
  • Video Detection Systems


NJDOT Rt. 35 Traffic Signal Improvements
$1,434,000.00 
Completion: January 2017
Intersection Improvements (13) including (6) temporary traffic signal systems. Full replacement of traffic signal poles, heads, controller cabinets, sidewalk, and ADA ramps.

NJDOT Traffic Signal Relamping South 2016
$1,956,535.00 
Completion: May 2018
Replacement of incandescent bulbs with new LEDs at various locations along NJDOT Roadways.

NJDOT Traffic Signal Relamping South 2016
$1,956,535.00 
Expected Completion: May 2019
Replacement of incandescent bulbs with new LEDs at various locations along NJDOT Roadways. This contract includes replacing traffic signal visors with new “snow-scoop” type visors to increase visibility in inclement weather.

Traffic Signal Contract 16 (NJDOT)
$37,631,000.00
Completed in the Year 2006
The contract work included a computerized traffic control system and fiber optic communications system for all of Southern New Jersey. Project included the installation of 80 miles of FO Cable, 22 Cameras, 11 Variable Message Signs, 89 Traffic Signal Intersections, 230,000 square feet of Milling and Paving, 40,000 Square Feet of Sidewalk, and 265 Traffic Foundations. Also included was the general construction of the South Traffic Operations Room and Computer Communication Room.

Traffic Signal Requirements (NYCDOT)
$13,597,000.00
Completed in the year 2010
This NYCDOT “Requirements” Contract included the installation of 150 new intersections which included 500+ new foundations, 500+ new poles, arms and Signals, 40,000 LF of Conduit with the associated restoration, and all associated cabling.

Traffic Signals Topics (NYCDOT)
$10,538,000.00
Completed in the year 2011
This NYCDOT “Topics” Contract included the installation of 2200 new ASTC Traffic Signal Controllers at Various Locations in the five boroughs. Work also includes the replacement of 15,000 incandescent bulbs with LEDs bulbs City wide.

Route 22 Traffic Signal Improvements / ITS Closed Loop System (NJDOT)

$7,777,000.00
Completed in the Year 2014
The contract work included the creation of an integrated system interconnecting eighteen traffic signals into one Controlled Traffic Signal System (CTSS). This includes the complete replacement of the existing traffic signal systems at five intersections and geometric improvements and signal modifications to seven other intersections. In addition, the project includes the installation of: Six new traffic cameras for the Camera Surveillance System (CSS), four (4) Travel Time System (TTS), two (2) new permanent electronic Dynamic Message Signs (DMS) and fiber optic wireless communication connecting the entire new integrated system to the Statewide Traffic Management Center in Woodbridge.

Traffic Signal Maintenance-Brooklyn December 2007 to February 2010 (NYCDOT)
$37,128,000.00
Completed in the year 2010

Traffic Signal Maintenance-Brooklyn March 2010 to November 2012 (NYCDOT)
$26,757,000.00
Completed in the year 2010

Traffic Signal Maintenance-Staten Island December 2007 to February 2010 (NYCDOT)

$8,356,000.00
Completed in the year 2012

Traffic Signal Contract #13 (NJDOT)
$6,100,000.00
Completed in the year 1998

Traffic Signal Contract #25 (NJDOT)

$4,719,000.00
Completed in the year 1997

Traffic Signal Maintenance-Staten Island March 2010 to November 2012 (NYCDOT)

$4,410,000.00
Completed in the year 2012

Intersection Improvements on Morris Ave. (Union County)
$3,086,000.00
Completed in the year 2006

South Orange Ave. Intersection Improvements (Essex County)
$2,422,000.00
Completed in the year 2007

Traffic Signal Group II (City of Camden)
$1,936,000.00
Completed in the year 2007

Hudson County Traffic Signals Package K (Hudson County)
$1,858,000.00
Completed in the year 2005

Train Preemption for Traffic Signals North II (NJDOT)
$1,695,000.00
Completed in the year 2013

Traffic Signal Package I (Hudson County)
$1,678,000.00
Completed in the year 2000

Various Intersections South 2000 (NJDOT)
$1,665,000.00
Completed in the year 2000

Newark Arena (Pruduntial Center) Exterior Circulation Improvements (Newark)
$1,596,000.00
Completed in the year 2008

Penn Station Exterior Circulation Improvements (NJ Transit)
$1,180,000.00
Completed in the year 2008

Central Ave Intersection Improvements (Union County)
$1,126,000.00
Completed in the year 2012

Terrill Rd Corridor Improvements (Union County)
$1,118,000.00
Completed in the year 2012

Bergen Town Center Intersection Improvements
$1,089,000.00
Completed in the year 2008

Installation of Battery Backup Systems (NYCDOT)
$1,048,000.00
Completed in the year 2008

Various Intersections North 2001 (NJDOT)
$784,000.00
Completed in the year 2001

Traffic Signal Relamping 2013 – Central (NJDOT)
$776,000.00
Completed in the Year 2013

Various Intersections North 2000 (NJDOT)
$767,000.00
Completed in the year 2000

Traffic Signal Relamping 2013 – North (NJDOT)
$600,000.00
Completed in the Year 2013

Various Intersections North 2002 (NJDOT)
$559,000.00
Completed in the year 2002

Various Intersections South 2002 (NJDOT)
$495,000.00
Completed in the year 2002

Central Traffic Signal Re-Lamping Contract 2011 (NJDOT)
$462,000.00
Completed in the year 2011

Rt 22 from Robin Hood Road to Fairview Drive (NJDOT)
$428,000.00
Completed in the year 2014

Route 1&9 and Delancy Street Improvements (NJDOT)
$188,000.00
Completed in the year 2010