Since 1929

Electronic Toll Collection Systems

Installation, Integration, and Maintenance of all components of Electronic Tolling Collection Systems including:

  • AVI Antennas
  • Vehicle Enforcement System Cameras
  • Overhead Vehicle Detectors
  • Treadles and Loops
  • Light Curtains
  • Lane Electronic Controllers
  • Patron Feedback Displays
  • Overhead Lane Signs
  • Conduit and Cabling
  • Testing

Completed in the year 2023
Maintenance of 82 Toll Lanes at all Port Authority Crossings including the GWB (Upper and Lower), Lincoln Tunnel, Holland Tunnel, Goethals Bridge, Bayonne Bridge, Outerbridge Crossing , and PIP. Work Started in 2006 and continued through 2023.

Completed in the year 2017
Implementation of a pilot program and permanent installation of Conduent’s Vehicle Passenger Detection Systems which can detect the number of passengers in cars in-transit. This system, the first of its kind in NYC, is located on I-278, The Staten Island Expressway, on the new cashless tolling gantry. This contract also includes 36 months of scheduled and on call maintenance.

Completed in the year 2006
Installation of EZPass Toll Lanes at New Toll Plazas 77, 89, and 15X on the Parkway and NJ Turnpike. The contract also installed High Speed EZPass Lanes at the Cape May, Toms River, Asbury, Raritan, Hillsdale, and 18W Toll Plazas. Lanes include the installation of cameras, tag readers, treadles, and light curtains and all associated Conduit, Communications, and Power Cables.

Completed in the year 1991
Installed a fully functional Toll Registration System at all Port Authority Crossings Toll Plazas including the GWB (Upper and Lower), Lincoln Tunnel, Holland Tunnel, Goethals Bridge, Bayonne Bridge, Outerbridge Crossing , and Palisades Interstate Parkway.

Completed in the year 2000
Installation of EZPass Toll Lanes at all Port Authority Crossings including Lincoln Tunnel, Holland Tunnel, GWB, Goethals Bridge, and Bayonne Bridge. Lanes include the installation of cameras, tag readers, treadles, and light curtains and all associated Comms and Power Cables.

Completed in the year 2018
This contract includes the electrical reconstruction of 66 EZ-Pass lanes, including the replacement of the most ETC components. Devices include Vehicle Enforcement Cameras, SICK Overhead Vehicle Sensors, LEC Lane Controllers, Lane Messaging Signs, AVI Antennas, toll booth canopy conduit, toll island concrete replacement, and new Close Up Lane Observation Cameras. All work is being performed on a lane by lane basis while keeping the existing system operational.

Completed in the year 2013
Removal and temporary reinstallation of the EZ-Pass devices onto temporary scaffolding to accommodate the installation of the new curtain wall at the Goethals Bridge. Upon completion of the curtain wall, removal and reinstallation of the system back to the permanent location.

Completed in the year 2008

Completed in the year 2013
Removal and Relocation of EZ-Pass equipment prior to deconstruction of 2 Lanes at Bayonne Bridge Toll Plaza, as part of the BBNCP master project.